Client
Brisbane Catholic Education
Location
Coomera, Gold Coast
Services
Bioretention basin rebuild, wetland rehabilitation
Duration
12 Weeks
The Challenge
The job was meant to be a strip and rectification of a failing bioretention basin. It turned into a full rebuild, carried out on a live school campus where access, timing and stormwater all worked against the crew.
The only truck route into the site crossed the school’s main footpath, so every vehicle movement needed a spotter, and any turf or planting damaged by access was repaired at the end of the job. During term, no vehicles could move between 7:30 and 9:00am or 2:00 and 3:30pm, so deliveries were timed around the school day. Most of the campus’s stormwater also drained straight into the work zone through two inlet pipes, which meant even light rain flooded the site. Coir logs and stockpiles were used to steer water away from the trimmed clay while works were underway.
Our Approach
Full system rebuild.
A conductivity test at the start of works showed the basin had failed well below the surface, so the filter media, drainage gravel, pipework and clay base were all replaced, relaid or re-graded rather than simply cleaned up.
Correcting the levels.
The forebay, dividing wall and drainage pits were all at odds with each other, which was stopping the system draining properly. The basin pit was lowered by around 150mm, and a new face and custom grate were cut into the wetland pit, so water now reaches both pits and drains as designed.
Wetland rehabilitation and forebay protection.
A severe Typha (bulrush) infestation was removed from the wetland, with coir logs and jute mesh used to stabilise the batters. Inlet grates were raised so debris passes underneath instead of clogging the pipes, and concrete blocks were placed in the forebay to slow inflows and catch debris before it reaches the basin.
Our Results
The basin now drains as it was designed to, with the media, gravel, pipework and base all rebuilt.
The wetland is cleared of Typha, replanted, and its batters are stabilised.
Inlets are flowing freely, with raised grates keeping debris clear of the pipes.
The forebay now protects the system, with concrete blocks slowing inflows and trapping debris.
The full rebuild was delivered safely across 12 weeks on a live school campus, with spotters on every vehicle movement.
TEC will carry out bi-monthly maintenance and watering through to September 2027, with monitoring for Typha regrowth and a site inspection after any heavy rain event.